The Home Building Process
Site Selection
Hollison Custom Homes assists you from start to finish including the selection of your home site. There are many factors to consider when searching for a home site. Size of the site, typography, school districts, vegetation, soil condition, subdivision or no subdivision, proximity to work etc. We can assist you in assessing the positive and negative aspects of potential home sites as they relate to construction.
Design
Once a homesite has been selected, we move in to the design phase. Designing your custom home can be the longest part of the process, but we feel it is imperative to spend more time designing to make sure your unique needs are being satisfied. In all cases, we will spend the necessary amount of time designing your custom plan and incorporating any revisions to create your blueprint.
Follow-up
Even after owners have moved in to their new homes, Hollison Custom Homes will maintain contact to ensure that customers are satisfied and do not have any issues or concerns. We pride ourselves on not only the quality of our work, but our ability to develop relationships with home owners.
Learn More About
Hollison Custom Homes
Discover Your Style
View Gallery
Let’s Get Started
Contact Us
Click here to see our Tentative Construction Schedule!
Tentative Homeowner Process & Selection Schedule | |||||
Construction Activity Description |
Critical Duration |
Complete | Project Start |
Project Completion |
|
Initial
Meeting & Introduction |
2 Weeks | Introductory Meeting | January 1, 2019 | Jamuary 15, 2019 | |
Share Building Experiences | |||||
Exchange References | |||||
Explore Owners Needs | |||||
Discuss Owner & Builder Expectations | |||||
Discuss Homebuilding Process | |||||
Commitment Project Development |
4 Weeks | Design-Build Commitment | January 15, 2019 | February 12, 2019 | |
Plan Development | |||||
Specification Development | |||||
Construction Schedule Development | |||||
Sales & Construction Agreement | |||||
Exterior
Material & Color Selection |
2 Weeks | Brick, Mortar, Stone, Siding, Roofing | February 12, 2019 | February 26, 2019 | |
Windows, Gutters, Entry Door Etc. | |||||
Interior
Material & Color Selections During Permitting, Sitework & Foundation |
4 Weeks | Architectural Review Board Submittal | February 26, 2019 | March 26, 2019 | |
Fireplace | |||||
Cabinetry & Countertops | |||||
Plumbing Fixtures | |||||
Appliances | |||||
Low Voltage (Security & A/V) | |||||
During Framing | 9 Weeks | Interior Trim Details | March 26, 2019 | May 28, 2019 | |
Interior Staircase Selections | |||||
Fireplace Surrounds & Mantles | |||||
Develop Paint Schedule | |||||
Flooring - Ceramic Tile | |||||
Flooring - Hardwood | |||||
Flooring - Carpeting | |||||
During Exterior Veneer Installation & Drywall Installation |
6 Weeks | Garage Doors | May 28, 2019 | July 9, 2019 | |
Electrical Fixtures | |||||
Door Hardware | |||||
Mirror & Shower Enclosure Selections | |||||
Bathroom Accessories | |||||
Closet Shelving | |||||
Landscaping & Outdoor Living Spaces | |||||
Driveway Layout | |||||
Mailbox Location | |||||
Estimated
Selection Completion Date Approximate Total Selection Period (Days) |
July 9, 2019 189 |